Lincoln St Project Update

7/02/2019 – McCabe is continuing to grade the street to the west.  They will be getting everything cleaned up from Stone to Water Street in preparation of this weekend’s festivities.

Beginning next week they will be starting on Phase 2 of the project.  They will begin removing pavement and concrete starting at Stone Street and working to the west.  Sidewalks will be left in place as long as possible.  However, we encourage businesses to utilize back entrances if possible.