TEST TW WEATHER

37°F

Lincoln St Project Update

05/28/2019 – McCabe is continuing to install services from Stone Street to the east.  They are focusing on Stone to Water Street right now.  They will probably be working towards Crocker Street by the end of the week.

Another crew will be coming in towards the end of this week to work on installing new storm sewer from Stone to the east.

Once all of the underground work is completed from Stone to Water Street they will begin grading the road to prepare for new curb and gutter and asphalt.